Default Resources

We have MS Project 2000. Can you print a schedule of resource assignments
based upon the resource. Example - if we have resources of Rob, Ken, Dan and
Rob is working on task 1 on Monday and Tuesday, task 2 on Wednesday and task
3 on Thursday and Friday, can you print out a schedule for Rob that shows
what his daily assignments are for the week.
Reply With Quote
Sponsored Links
  #2  
Old 05-03-2007, 10:05 PM
Bob I
 
Posts: n/a
Default Re: Resources

If you don't receive an answer here you may pose your question to the
folks in the Project group.
news://msnews.microsoft.com/microsoft.public.project

Ken Starlin wrote:
> We have MS Project 2000. Can you print a schedule of resource assignments
> based upon the resource. Example - if we have resources of Rob, Ken, Dan and
> Rob is working on task 1 on Monday and Tuesday, task 2 on Wednesday and task
> 3 on Thursday and Friday, can you print out a schedule for Rob that shows
> what his daily assignments are for the week.


Reply With Quote
Sponsored Links
Fix your Windows Problems - FAST.
FREE Safe Scan Registry Check. Locate & Fix Errors in Minutes!

Powered by vBulletin® Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
LinkBacks Enabled by vBSEO 3.1.0
© 2004 - 2007 Web-S-Sense Pty. Ltd. Usenet and forums posts © their respective authors.
Ad Management by RedTyger