1) The MS Project Server 2003 implemention uses managed time periods to
report time on a weekly basis. When a resource enters time across multiple
weeks (Week1 and Week2 for example) and uses the update all button for week2,
MS Project Server submits only the hours entered for week2 to the resource
manager for Approval while the hours for week1 and week2 are submitted to the
project manager. Is there a work around for this?

2) SP2a has been installed for Project Server 2003. When a new resource is
added to MS Project Server 2003, there are notification on the resource's
home page stating that there are unsubmitted timesheets for weeks prior to
the date of join for that resource. The SP2a claims to have a fix for this
issue. Is this because the resource has been assigned to tasks that start
even before the date of join to this new resource? Is there a work around for
this issue?
Reply With Quote
Sponsored Links
  #2  
Old 05-22-2007, 10:58 PM
Og
 
Posts: n/a
Default Re: MS Project Server 2003

"Jag" <Jag@discussions.microsoft.com> wrote in message
news:03901253-06B4-4D38-8F65-AD84F12E550C@microsoft.com...
> 1) The MS Project Server 2003 implemention uses managed time periods to
> report time on a weekly basis. When a resource enters time across multiple
> weeks (Week1 and Week2 for example) and uses the update all button for
> week2,
> MS Project Server submits only the hours entered for week2 to the resource
> manager for Approval while the hours for week1 and week2 are submitted to
> the
> project manager. Is there a work around for this?
>
> 2) SP2a has been installed for Project Server 2003. When a new resource is
> added to MS Project Server 2003, there are notification on the resource's
> home page stating that there are unsubmitted timesheets for weeks prior to
> the date of join for that resource. The SP2a claims to have a fix for this
> issue. Is this because the resource has been assigned to tasks that start
> even before the date of join to this new resource? Is there a work around
> for
> this issue?


Project is _not_ one of the applications that comprise the Microsoft Office
suite, which is what this newsgroup deals with.
Please visit one of the Project Server newsgroups:
microsoft.public.project.pro_and_server
microsoft.public.project.server
Steve


Reply With Quote
Sponsored Links
Fix your Windows Problems - FAST.
FREE Safe Scan Registry Check. Locate & Fix Errors in Minutes!
Reply


Thread Tools
Display Modes


Similar Threads
Thread Thread Starter Forum Replies Last Post
system requirements for Project 2000, 2003, 2007 ? Mr. Swamy Microsoft Office 1 05-21-2007 04:16 AM
Vista Ping 2003 Server shauncarter1 Windows Vista 4 04-24-2007 06:13 AM
lsass.exe error on Windows 2003 server Geof.chirwa@gmail.com Windows XP 2 04-03-2007 03:04 AM
lsass.exe error on Windows 2003 server Geof.chirwa@gmail.com Windows XP 1 04-02-2007 04:35 PM
Can office 2007 be used on a server with server 2003? Aaron Microsoft Office 3 04-01-2007 01:01 AM


All times are GMT. The time now is 05:35 PM.


Powered by vBulletin® Copyright ©2000 - 2008, Jelsoft Enterprises Ltd.
LinkBacks Enabled by vBSEO 3.1.0
© 2004 - 2007 Web-S-Sense Pty. Ltd. Usenet and forums posts © their respective authors.
Ad Management by RedTyger