I am trying to schedule projects: I need a start date, finish date ( that is
7 days duration) I also need another start and finish date ( that is 5 days).
Whenever I make a new column it adjusts the original start date. Even if I
use start2 and finish2.
If I could get some help, I would really appreciate it.
> I am trying to schedule projects: I need a start date, finish date ( that is
> 7 days duration) I also need another start and finish date ( that is 5 days).
> Whenever I make a new column it adjusts the original start date. Even if I
> use start2 and finish2.
> If I could get some help, I would really appreciate it.
>