PostPosted: Tue May 22, 2007 3:41 pm    Post subject: MS Project Server 2003 Reply with quote

1) The MS Project Server 2003 implemention uses managed time periods to
report time on a weekly basis. When a resource enters time across multiple
weeks (Week1 and Week2 for example) and uses the update all button for week2,
MS Project Server submits only the hours entered for week2 to the resource
manager for Approval while the hours for week1 and week2 are submitted to the
project manager. Is there a work around for this?

2) SP2a has been installed for Project Server 2003. When a new resource is
added to MS Project Server 2003, there are notification on the resource's
home page stating that there are unsubmitted timesheets for weeks prior to
the date of join for that resource. The SP2a claims to have a fix for this
issue. Is this because the resource has been assigned to tasks that start
even before the date of join to this new resource? Is there a work around for
this issue?
Back to top
Fix your Windows Problems - FAST.
FREE Safe Scan Registry Check. Locate & Fix Errors in Minutes!
Display posts from previous:   
Post new topic   Reply to topic    Index -> Microsoft Office All times are GMT
Page 1 of 1

 

 MemberlistMemberlist  UsergroupsUsergroups



Powered by p|-|pBB

Featured Sites: DIY Projects